Meeting minutes 22/11/11

Collaboarative work session:

Dave - Decided upon a cable to be used, has set in motion the finalized search shift from general products to specifics in the rest of the group.

  • Calculated bandwidth requirement
  • Determined the dispersion
  • Sketched a rough power budget to work out the necessary power/attenuation/coefficents for the remaining components.
  • Detector has max input power of 10mW, we used this for the basis for the power budget. A 1W LED would fit our need.
  • Shifted search focus from Cable to LED, began to consider SLED.
  • Connectors - adapters available for connection to equipment.
  • Fusion splicing for connecting cable to cable ends.
Leanne - Find a 1W SLED suitable for use with the Fiber Optic cable.
Alan - With knowledge of the cable reduce power loss associated with splicing.
Will - Widen the knowledge of available detectors in case no suitable LED is found.

Further discussion in the preparation of the report went ahead. Idea to create different sections than our research goals with the aim of fluidity.
Leanne - Started the Presentation, decided upon a theme and order.



NOTE the usual meeting on Wednesday  23/11/11 has been turned into a Q and A with the Client due to the success of todays meeting and Leanne's absence.